MID Information Release
The McHenry Solar Farm - California Environmental Quality Act (CEQA)
As a result of MID's request for offers for renewable energy projects, SunPower Corporation (SunPower) offered the purchase of electricity output from the McHenry Solar Farm, a proposed local solar photovoltaic (PV) project. This proposed project is a 154-acre, 25 MW solar PV project that would be developed by SunPower on the corner of McHenry Avenue and Ladd Road in northeast Modesto.
At this time,SunPower has prepared a Draft Environmental Impact Report (EIR) for the project. The Board of Directors will consider the approval of an EIR and a Large Generator Interconnection Agreement at its regularly scheduled meeting on Tuesday July 26, 2011. The project would add approximately two percent renewable energy to MID's power resources starting in 2012.
The public has had several opportunities to provide comments and feedback throughout this process. Information regarding the process, documents and previous meetings is posted below.
Schedule
| Notice of Preparation: |
Comment period - December 6, 2010 - January 5, 2011 |
| Notice of Availability: |
Comment period - May 18, 2011 - July 5, 2011 |
| Draft EIR: |
McHenry Solar Farm
Draft Environmental Impact Report |
| Public Comment Workshop: |
Thursday, June 16, 2011, 7pm - 9pm
MID's Downtown Office
1231 11th Street, Modesto , CA 95354
(Please use employee entrance on L Street side of the building.) |
| Public Meeting - Consideration of Final EIR |
Tuesday, July 26, 2011, 9am
MID's Downtown Office
1231 11th Street, Modesto , CA 95354
MID Board Room
|
| |
Final EIR (PDF) |
Previous public outreach information outside of the CEQA process can be found here: http://www.mid.org/solarfarm/outreach/
For more information, please contact:
David Olivares
P.O. Box 4060
Modesto, CA 95352
(209) 526-7595
davido@mid.org
|