Don Pedro Board of Control Report
Water Use
Manager Joe Lima reported that the Don Pedro
Board of Control had expenditures of $1,776,000
and revenue of $1,966,000 between Jan. 1 and
Oct. 31, 2006. Reservations between Jan. 1 and
Nov. 30 were 7,766, compared to 7,467 in the
same time period the previous year.
Board action
The Board unanimously approved
the following four items:
- An open purchase
order to Agriculture Priority Pollutants Laboratory,
Inc. to analyze MID water samples for chemical
residue as required by the Conditional Waiver
of Waste Discharge (Ag Waiver) for discharges
from agricultural lands.
- The agreement for
independent engineering evaluation for the
Phase Two Expansion of the Modesto Regional
Water Treatment Plant with R.W. Beck, Inc.,
in an amount not-toexceed $83,600. This report
will provide the financial community with an
independent opinion as to the viability of
the project prior to the sale of bonds.
- The
Investment Policy Statement for the Retiree
Medical Benefits Plan revised December 2006.
Provides for the same asset allocation mix
as the MID Basic Plan Investment Policy and
allows the health care benefits assets to be
invested in areas that are likely to achieve
higher long-term earnings than are expected
under the present investment policy.
- Agreements
between MID and SunGard Corbel LLC for Relius
software licenses, support and consulting,
as well as future incremental licenses, support,
and upgrades to maintain software application
continuity for the Relius product. This replaces
the existing software that is 12 years old,
no longer supported by the vendor, and can
no longer meet the functional requirements
needed for retirement record keeping.
Billing System
Update Assistant
General Manager Lou Hampel, Finance, reported
that billing system to-date expenditures have
been $6.848 million, slightly under the $6.898
million budget (includes software, licenses,
training, maintenance and hardware). He noted
that while staff has allocated $5.8 million in
time to the project since it began in 2003, no
new staff members were hired for the project.
He added that any system requires on-going staff
time.
|